1, Equipment support or hanging equipment.
When the equipment, to the root leveling, and then in accordance with the support or hanging equipment parts diagram and sieve equipment diagram, the order installed each part.
Before loading, the spring should be selected according to the practical stiffness value of the end face symbol.
2. Connect the screen box on the supporting or hanging equipment.
After installation, it should be adjusted according to the specified inclination.
With regard to the hanging sieve, the Angle of the sieve case and the horizontal spindle of the sieve case should be adjusted simultaneously.
Generally, the first horizontal adjustment to eliminate the deflection of the screen box.
After the horizontal correction, the longitudinal inclination Angle of the screen box is adjusted.
The stress of the vibration isolation spring should be even, and its stress can be judged by measuring the tension of the spring.
In general, the two groups of tension at the feed end of the same amount of tension, discharge end of the two groups of tension springs should be so.
The amount of tension between the discharging end and the feeding end can be different.
3. Equipment motor and triangular tape.
When using the equipment, the base of the motor should be leveled, the horizontal requirements of the motor should be corrected, the center lines of the corresponding grooves of the two rubber belt wheels should coincide, and the tension requirements of the triangular belt should be appropriate.
4. Fix the screen surface according to the requirements.
5. Check the fixed status of the connecting parts of the screen,such as the screen plate and vibrator, etc. The screen should be tensioned evenly to prevent partial vibration.
Check the lubrication condition of the transmission part, whether the wiring of the motor and control box is correct, and use the hand to roll the transmission part to check whether the operation is normal.
6. Check the feeding and discharging chute of the sieve and the bottom funnel of the sieve.